Project Timeline

Project Process

Blog 5

We Will Make Your Liquid Dreams Come True In Just 6 Weeks


F.M. Pool Construction is a full-service company with over 40 years of experience in the industry. We will build your pool to your expectations and have it done within six weeks if you are having the basics done. If you require more, like an additional deck or gazebo, the process will take a little longer.

Project Preparation Pre-dig:


You will meet with a member of our staff and go over design ideas and sign your contract.

Week 1


Excavation, Plumbing, Steel, Electrical

Week 2


Pre-Gunite Inspection, Gunite Applied and Rock Work Prep

Week 3


Tile Installation, Coping and Decking

Week 4


Equipment Set, Final Electrical, Prep for Plaster and Concrete Installation

Week 5


Pre-Plaster Inspection, Plaster, Startup and Instructions

Week 6


Pool Party!!